Cyprus takes 63% of cable costs

✦
Written by AIto brief AI · 15 November 2026, 01:50
How it was written

Cyprus takes on most of the cost before the connection takes shape.

Image composition · tobrief
the text · 3 min read

Cyprus has been assigned 63% of the construction bill for the Great Sea Interconnector, a planned power cable to Crete, while Greece takes 37% (Cyprus Mail). Greece's grid operator ADMIE expects the link to be energized, meaning it carries power for the first time, in the second half of 2031 (ADMIE, ADMIE). On 20 October, Cyprus's energy regulator told parliament that cable maker Nexans now expects completion by 1 January 2031 (Cyprus News Agency, Philenews).

Neither date is new. Greek outlets reported the later one on 14 November as fresh news (ERT), but ADMIE had published it for consultation in September. The slip happened earlier. ADMIE's previous draft plan pointed to 2029 (ADMIE), and no one has explained why the Greek and Cypriot estimates still differ.

What Cyprus has signed up to pay for

The cable is meant to end Cyprus's electrical isolation from the rest of the EU (European Commission). Crete already connects to mainland Greece. ADMIE plans an 898-kilometre, 1,000-megawatt link from there and puts the cost of its section at €1.94 billion (ADMIE).

Brussels has already chipped in. In January 2022 the EU awarded a grant of about €657 million towards the project (CINEA). The 63/37 split covers what regulators call eligible construction investment, the building costs the two countries agreed to divide between them.

Cyprus pledged €25 million a year from 2025 towards its share, but the first payment was still outstanding on 20 October (Stockwatch).

Why 2031 is still a guess

The seabed comes first. The route reaches roughly 3,000 metres deep, and ADMIE put the share of completed surveys at 60% (ADMIE). Polyvios Lemonaris, president of the Cypriot regulator CERA, told MPs the rest might take about six months (Philenews).

Those surveys carry two risks. If they force a new route, CERA warned, the cost goes up (Stockwatch). Survey work also resumed this month only after Turkey issued a navigational warning claiming authority over part of the route (To Brief), though Greek reporting says it continues under Greek authorization (eKathimerini).

Then the cable has to be made. Nexans won that contract in 2023 for about €1.43 billion, and in January it said it was examining an adjusted schedule with its client (Nexans, Nexans). Its chief executive has said he envisages restarting production for the project in 2028 (Kathimerini Cyprus).

Each end also needs a converter station. Household grids run on alternating current, which flips direction constantly, while long subsea cables carry direct current, so converters translate between the two. ADMIE has only a preferred bidder, Siemens, and technical studies are still deciding exactly what it will build (ADMIE). The link can be switched on only after cable, converters and land connections are tested together.

Cheaper power on paper, not yet on bills

The promised savings come from a model. A simulation by Aristotle University of Thessaloniki found Cypriot wholesale prices, what power producers charge electricity retailers, 19% lower with the link in one 2035 scenario (Euro2day).

That gain depends on how expensive Cyprus's own power is. If cheaper local gas brings generation costs down, there is less to save by importing. The study found that case could shrink the yearly benefit to roughly €40–50 million (Euro2day). Separately, it found Greek consumers gain little in any scenario.

A lower wholesale price is also not a lower household bill. Bills include network charges, which pay for grid infrastructure such as cables. If Cyprus's construction share is recovered that way, higher charges would eat into whatever wholesale saving the link delivers.

The record supports a narrower claim than cheaper power by 2031. Cyprus has accepted the larger share of construction costs before a converter contract is signed, before the seabed is fully mapped, and before ADMIE and Nexans have a firm installation schedule. Until those exist, the date that matters most is the 2028 production restart Nexans has floated (Kathimerini Cyprus), not 2031.

Stocks in this story

Details about this article
Model:
claude-opus-5-5
Generated:
11/15/2026, 1:49:19 AM
Pipeline run:
eu_pipeline_20261115_005007
Watermark:
SynthID (Google's invisible watermark)
Human review:
None before publication
Learn more about our methodology →